在项目执行两年后,项目经理确信项目范围将按照承诺交付,项目团队按计划工作,所有问题都得到迅速解决,在完成日期前两个月,首席执行官命令执行一项范围变更,项目经理应该怎么做?Two years after the project was implemented,the project manager is confident that the scope will be delivered as promised,The team is working as planned, and all issues are resolved quickly.Two months before the completion date, the CEO orders a change in scope.What should the project manager do?()
(A):因为会对进度和预算产生负面影响,建议首席执行官重新考虑该范围变更Suggest that the CEO reconsider the scope change due to negative impact on schedule and budget
(B):向首席执行官询问该范围变更的原因,讨论潜在影响,然后采取适当的措施Ask the CEO about the reasons for the scope change, discuss the potential impact, and then take appropriate steps
(C):告知首席执行官,必须通过适当的渠道进行该范围变更Inform the CEO that the scope change must be done through the proper channels
(D):向前推进并按要求记录该范围变更Move forward and document the scope change as required
查看解析
参考答案
继续答题:下一题
更多PMP试题
- 1在项目章程获得批准,实施新的会计制度之后,项目经理试图了解会计部门的结构和流程。项目经理下一步应该创建什么?Following project charter approval to implement a new accounting system.the project manager tries to understand the accounting department’s structure and processes.What should the project manager create next?()
- 2为了控制进度,项目经理重新分析项目,以使预测项目的历时。他按进度安排弹性最小的活动来排序,它采用的是什么技术:
- 3一个项目涉及位于全球各地的团队成员,产生了许多不同意见,新项目经理通过成功协助团 队协作和问题解决提高生产力。项目经理使用的是什么工具或技术?
- 4一家公司以前习惯釆用预测型的方法管理项目,现在刚刚引进敏捷适应型的方法来管理项目,首席技术 官(CT0)担心项目团队是否可以顺利开展定义范围过程的活动。项目经理应该如何做才能确保完整定义项目范围?
- 5一项产品已经交付给客户进行测试验收,但由于产品未经外部检查机构的审计,客户拒收产品,项目经理下一步该怎么做
- 6项目经理应使用什么工具来向客户证明最终产品需求满足业务需求?What tool should the project manager use to demonstrate to the customer that the final product meets the business needs?()